Client

Wincasa, Winterthur

Location

Hebelstrasse 82, Maiengasse 12/14/16, Friedensgasse 19, Basel

Use

5 multi-dwelling units with a total of 74 apartments and a communal swimming pool

Key Dates

1980 | Completion of original building
2010 | Start of construction
2012 | Completion

Our Role

General planner on behalf of the owner

Our Tasks

Structural component analysis, condition analysis, total contractor tender, pre-project, planning application, executive planning, creative direction